- Launched
- May 20233 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 8 of 989% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 9 units
Rehab8 units for existing members
Total 17 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 16
- 3 BHK
- 1
- Total units
- 17
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 8 | |
| 0% | 0% | 0% | 9 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Rekha Chsl by D S M Group is a 17-unit BMC-sanctioned project in Goregaon West, Mumbai 400062, launched in May 2023 with possession due in December 2026. 8 units booked out of 9 units for sale. The concrete structure (RCC) is complete.
Read full summary
Rekha Chsl is a BMC-sanctioned project by D S M Group in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800050959. It was launched in May 2023. It has 17 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 17 units, 9 are for sale and 8 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
8 units booked out of 9 units for sale (89%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.