Giriraj, Borivali East
by Go Developer · Borivali East, Mumbai 400066 · Map
- Launched
- May 20232 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 4 of 1040% · 6 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 10 units
Rehab6 units for existing members
Land-owner share4 units, not for sale
Total 20 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 4
- 1 BHK
- 15
- 2 BHK
- 1
- Total units
- 20
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 10
- Rehab units
- 6
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 4 | |
| 100% | 100% | 0% | 3 | |
| 100% | 100% | 0% | 3 | |
| 100% | 45% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400066
Projects with 10–40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 2 yrs 9 mths |
| Possession date extended | By 1 yr | 2 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Jun 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 40% | 86% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Balaji Darshan, Borivali East
- Rishabh Sadhana, Borivali East
- Arvind Niwas, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Balaji Darshan | June 2023 | December 2027 | 100% | 12 units booked out of 14 units for sale |
| Rishabh Sadhana | March 2023 | December 2025 | 0% | 3 units booked out of total 19 units |
| Arvind Niwas | August 2023 | June 2026 | 100% | 26 units booked out of 26 units for sale |
About this project
Giriraj by Go Developer is a 20-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in May 2023 with possession due in December 2026. 4 units booked out of 10 units for sale. The concrete structure (RCC) is complete.
Read full summary
Giriraj is a BMC-sanctioned project by Go Developer in Borivali East, Mumbai 400066, registered with MahaRERA as P51800051058. It was launched in May 2023. It has 20 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 10 are for sale, 6 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.
4 units booked out of 10 units for sale (40%). Since the July 2026 update, 1 more unit has been booked.