Somani 72 East, Chandivali

by Nircon Developers Pvt Ltd · Chandivali, Mumbai 400072 · Map

Launched
May 20232 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Nearing possession
Booked
0 of 840%
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
26
2 BHK
57
Other units
1
Total units
84
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 25%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%0
100%75%0%0
100%75%0%0
100%25%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Somani 72 East by Nircon Developers Pvt Ltd is an 84-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in May 2023 with possession due in December 2026. 0 units booked out of total 84 units. The concrete structure (RCC) is complete.

Read full summary

Somani 72 East is a BMC-sanctioned project by Nircon Developers Pvt Ltd in Chandivali, Mumbai 400072, registered with MahaRERA as P51800051115. It was launched in May 2023. It has 84 units in 2 buildings: 83 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.

0 units booked out of total 84 units (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 75% to 100%.