by Bhoomi Shashwat Estate Pvt Ltd · Borivali West, Mumbai 400091 · Map

Launched
May 20233 yrs 5 mths promised
Possession (MahaRERA)
Oct 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
110 of 12787% · 169 rehab units
Buildings
51.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale110 booked out of 127 units

Rehab169 units for existing members

Total 296 units. Rehab units are not for sale.

Project facts

1 BHK
37
2 BHK
204
3 BHK
54
4 BHK
1
Total units
296
Buildings
5
Land
1.9 acres
Phases
1
MahaRERA complaints
0
Free-sale units
127
Rehab units
169

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 46%Dec 2025: Concrete structure (RCC) 78%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%110
100%100%80%110
100%78%0%111
100%46%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Bhoomi Pratishtha by Bhoomi Shashwat Estate Pvt Ltd is a 296-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in May 2023 with possession due in October 2026. 110 units booked out of 127 units for sale. The concrete structure (RCC) is complete.

Read full summary

Bhoomi Pratishtha is a BMC-sanctioned project by Bhoomi Shashwat Estate Pvt Ltd in Borivali West, Mumbai 400091, registered with MahaRERA as P51800051136. It was launched in May 2023. It has 296 units in 5 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 296 units, 127 are for sale and 169 are rehab units for existing members.

Its registered possession date is October 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

110 units booked out of 127 units for sale (87%).