Skip to main content

Jangid Trinity, Borivali East

by Jangid Construction P LTD · Borivali East, Mumbai 400066 · Map

Launched
Jul 20234 yrs 5 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
37%Mid-construction
Booked
308 of 33293% · 254 in Jul 2026
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
332
Total units
332
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)37%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 30%Jul 2026: Concrete structure (RCC) 30%Oct 2026: Concrete structure (RCC) 37%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 37%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%37%0%308
100%30%0%254
100%30%0%254
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Jangid Trinity by Jangid Construction P LTD is a 332-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in July 2023 with possession due in December 2027. 308 units booked out of total 332 units. The concrete structure (RCC) is 37% complete.

Read full summary

Jangid Trinity is an SRA-sanctioned project by Jangid Construction P LTD in Borivali East, Mumbai 400066, registered with MahaRERA as P51800051923. It was launched in July 2023. It has 332 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 37% complete, final finishes not started.

308 units booked out of total 332 units (93%). Since the July 2026 update, 54 more units have been booked and the reported concrete structure (RCC) has gone from 30% to 37%.