Jangid Trinity, Borivali East
by Jangid Construction P LTD · Borivali East, Mumbai 400066 · Map
- Launched
- Jul 20234 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 37%Mid-construction
- Booked
- 308 of 33293% · 254 in Jul 2026
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 332
- Total units
- 332
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 37% | 0% | 308 | |
| 100% | 30% | 0% | 254 | |
| 100% | 30% | 0% | 254 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Jangid Trinity by Jangid Construction P LTD is a 332-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in July 2023 with possession due in December 2027. 308 units booked out of total 332 units. The concrete structure (RCC) is 37% complete.
Read full summary
Jangid Trinity is an SRA-sanctioned project by Jangid Construction P LTD in Borivali East, Mumbai 400066, registered with MahaRERA as P51800051923. It was launched in July 2023. It has 332 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 37% complete, final finishes not started.
308 units booked out of total 332 units (93%). Since the July 2026 update, 54 more units have been booked and the reported concrete structure (RCC) has gone from 30% to 37%.