Fortune Florence, Borivali East

by Fortune Acres Private Limited · Borivali East, Mumbai 400066 · Map

Launched
Jul 20233 yrs 10 mths promised
Possession (MahaRERA)
May 2027Not extended
Concrete structure
58%Mid-construction
Booked
321 of 38883% · 275 in Jul 2026
Buildings
21.1 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
238
3 BHK
128
Other units
22
Total units
388
Buildings
2
Land
1.1 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)58%
Finishes, lifts and services3%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 98%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 53%Dec 2025: Concrete structure (RCC) 4%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 58%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 3%Excavation 100%Concrete structure (RCC) 58%Final finishes 3%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%58%3%321
100%25%0%275
98%4%0%222
75%53%0%115

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400066

Projects with 150–800 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths5 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)May 2027Aug 2028
Concrete structure (RCC)58%100%
Units booked83%95%
MahaRERA complaints (filed by or against the builder)20

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Fortune Florence by Fortune Acres Private Limited is a 388-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in July 2023 with possession due in May 2027. 321 units booked out of total 388 units. The concrete structure (RCC) is 58% complete.

Read full summary

Fortune Florence is an SRA-sanctioned project by Fortune Acres Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800052043. It was launched in July 2023. It has 388 units in 2 buildings: 366 homes (2 and 3 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is May 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 58% complete, final finishes 3% complete.

321 units booked out of total 388 units (83%). Since the July 2026 update, 46 more units have been booked and the reported concrete structure (RCC) has gone from 25% to 58%.