Signature, Vikhroli

by Agastya Infra · Vikhroli, Mumbai 400083 · Map

Launched
Jul 20232 yrs 9 mths originally promised
Possession (MahaRERA)
Nov 2026Extended by 7 mths
Concrete structure
88%Mid-construction
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)88%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 79%Dec 2025: Concrete structure (RCC) 88%Jul 2026: Concrete structure (RCC) 88%Oct 2026: Concrete structure (RCC) 88%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 88%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%88%0%114
100%88%0%–
100%88%0%–
100%79%0%114

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Signature by Agastya Infra is a MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in July 2023 with possession due in November 2026. The concrete structure (RCC) is 88% complete.

Read full summary

Signature is a MHADA-sanctioned project by Agastya Infra in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800052112. It was launched in July 2023. Its MahaRERA status is Active.

Its registered possession date is November 2026, extended by 7 months from the original April 2026. Construction: excavation complete, structure (RCC) 88% complete, final finishes not started.