Rekha Pragati, Andheri East
by Milan Lekh Realty · Andheri East, Mumbai 400069 · Map
- Launched
- Jul 20232 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr 1 mth
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 12 of 2255%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 22 units
Land-owner share15 units, not for sale
Total 37 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 19
- 2 BHK
- 18
- Total units
- 37
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Land-owner share (not for sale)
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 12 | |
| 100% | 90% | 0% | 12 | |
| 100% | 60% | 0% | – | |
| 100% | 60% | 0% | 5 |
"–" means MahaRERA shows no figure for that update.
About this project
Rekha Pragati by Milan Lekh Realty is a 37-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in July 2023 with possession due in December 2026. 12 units booked out of 22 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Rekha Pragati is a BMC-sanctioned project by Milan Lekh Realty in Andheri East, Mumbai 400069, registered with MahaRERA as P51800052159. It was launched in July 2023. It has 37 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 37 units, 22 are for sale and 15 are the land-owner's share, not for sale.
Its registered possession date is December 2026, extended by 1 year 1 month from the original November 2025. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
12 units booked out of 22 units for sale (55%).