Ambit Vista, Santacruz East
by Ambit Builders & Developers · Santacruz East, Mumbai 400055 · Map
- Launched
- Aug 20232 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked
- 84 of 10382%
- Buildings
- 40.6 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 7
- 2 BHK
- 56
- 3 BHK
- 28
- Other units
- 12
- Total units
- 103
- Buildings
- 4
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 35% | 84 | |
| 100% | 100% | 0% | 84 | |
| 100% | 100% | 0% | 80 | |
| 0% | 0% | 0% | 45 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400055
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 4 mths | 3 yrs |
| Possession date extended | By 1 yr | 1 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 80% |
| Units booked | 82% | 47% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 5 projects
- Royal Residency, Santacruz East
- Crystal Avenue, Santacruz East
- Maitri Enclave, Santacruz East
- Redevelopment Of Jamuna Mahal Chsl, Santacruz East
- Paradise Palace, Santacruz East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Royal Residency | July 2023 | December 2026 | 80% | 11 units booked out of total 53 units |
| Crystal Avenue | June 2023 | November 2026 | 100% | 46 units booked out of 67 units for sale |
| Maitri Enclave | December 2023 | December 2026 | 10% | 17 units booked out of 36 units for sale |
| Redevelopment Of Jamuna Mahal Chsl | December 2023 | May 2027 | 100% | 27 units booked out of 36 units for sale |
| Paradise Palace | January 2024 | December 2026 | 0% | 32 units booked out of 70 units for sale |
About this project
Ambit Vista by Ambit Builders & Developers is a 103-unit SRA-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2023 with possession due in December 2026. 84 units booked out of total 103 units. The concrete structure (RCC) is complete.
Read full summary
Ambit Vista is an SRA-sanctioned project by Ambit Builders & Developers in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800052265. It was launched in August 2023. It has 103 units in 4 buildings: 91 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 35% complete.
84 units booked out of total 103 units (82%).