Sai Shrushti, Chembur
by Shree Sai Realtors · Chembur, Mumbai 400071 · Map
- Launched
- Aug 20234 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 237 of 26589% · 256 rehab units
- Buildings
- 10.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale237 booked out of 265 units
Rehab256 units for existing members
Total 521 units. Rehab units are not for sale.
Project facts
- 1 RK
- 448
- Other units
- 73
- Total units
- 521
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 265
- Rehab units
- 256
- Reserved units
- 223
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | 237 | |
| 100% | 100% | 75% | 237 | |
| 100% | 100% | 75% | 237 | |
| 100% | 100% | 25% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sai Shrushti by Shree Sai Realtors is a 521-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in August 2023 with possession due in December 2027. 237 units booked out of 265 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sai Shrushti is an SRA-sanctioned project by Shree Sai Realtors in Chembur, Mumbai 400071, registered with MahaRERA as P51800052293. It was launched in August 2023. It has 521 units in 1 building: 448 homes (1 RK) and 73 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 521 units, 265 are for sale and 256 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.
237 units booked out of 265 units for sale (89%).