The Konark Rise, Borivali West

by Konark Rajendra Shah · Borivali West, Mumbai 400092 · Map

Launched
Aug 20232 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 1 yr 9 mths
Concrete structure
100%Nearing possession
Booked
5 of 1631%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
16
Total units
16
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%5
100%90%0%5
100%80%0%1
100%20%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Konark Rise by Konark Rajendra Shah is a 16-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in August 2023 with possession due in December 2027. 5 units booked out of total 16 units. The concrete structure (RCC) is complete.

Read full summary

The Konark Rise is a BMC-sanctioned project by Konark Rajendra Shah in Borivali West, Mumbai 400092, registered with MahaRERA as P51800052330. It was launched in August 2023. It has 16 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 1 year 9 months from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

5 units booked out of total 16 units (31%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 100%.