Sidhivinayak Orchid, Ghatkopar East

by Sidhivinayak Developers · Ghatkopar East, Mumbai 400075 · Map

Launched
Aug 20233 yrs 4 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
50%Mid-construction
Booked
2 of 2100%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
2
Total units
2
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%2
50%25%0%–
50%25%0%–
100%50%0%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sidhivinayak Orchid by Sidhivinayak Developers is a 2-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in August 2023 with possession due in December 2026. 2 units booked out of total 2 units. The concrete structure (RCC) is 50% complete.

Read full summary

Sidhivinayak Orchid is a MHADA-sanctioned project by Sidhivinayak Developers in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800052348. It was launched in August 2023. It has 2 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

2 units booked out of total 2 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 25% to 50%.