Shree Gopal, Jogeshwari East
by Dipti Builders Universal Pvt Ltd · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Aug 20234 yrs 8 mths promised
- Possession (MahaRERA)
- Apr 2028Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 84 of 17448% · 90 rehab units
- Buildings
- 10.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale84 booked out of 174 units
Rehab90 units for existing members
Total 264 units. Rehab units are not for sale.
Project facts
- Other units
- 264
- Total units
- 264
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 174
- Rehab units
- 90
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 65% | 84 | |
| 100% | 90% | 50% | 81 | |
| 100% | 75% | 15% | 68 | |
| 100% | 20% | 5% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Shree Gopal by Dipti Builders Universal Pvt Ltd is a 264-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in August 2023 with possession due in April 2028. 84 units booked out of 174 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Shree Gopal is a BMC-sanctioned project by Dipti Builders Universal Pvt Ltd in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800052352. It was launched in August 2023. It has 264 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 264 units, 174 are for sale and 90 are rehab units for existing members.
Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 65% complete.
84 units booked out of 174 units for sale (48%). Since the July 2026 update, 3 more units have been booked.