by Arham Realty · Vile Parle West, Mumbai 400056 · Map

Launched
Aug 20233 yrs 4 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
13 of 1493% · 13 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 14 units

Rehab13 units for existing members

Total 27 units. Rehab units are not for sale.

Project facts

2 BHK
1
3 BHK
22
Other units
4
Total units
27
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%13
100%100%80%13
100%100%25%13
100%100%25%11

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Meera Kunj by Arham Realty is a 27-unit project in Vile Parle West, Mumbai 400056, launched in August 2023 with possession due in December 2026. 13 units booked out of 14 units for sale. The concrete structure (RCC) is complete.

Read full summary

Meera Kunj is a project by Arham Realty in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800052395. It was launched in August 2023. It has 27 units in 1 building: 23 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 14 are for sale and 13 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

13 units booked out of 14 units for sale (93%).