Meera Kunj, Vile Parle West
by Arham Realty · Vile Parle West, Mumbai 400056 · Map
- Launched
- Aug 20233 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 13 of 1493% · 13 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 14 units
Rehab13 units for existing members
Total 27 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 1
- 3 BHK
- 22
- Other units
- 4
- Total units
- 27
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 14
- Rehab units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 13 | |
| 100% | 100% | 80% | 13 | |
| 100% | 100% | 25% | 13 | |
| 100% | 100% | 25% | 11 |
"–" means MahaRERA shows no figure for that update.
About this project
Meera Kunj by Arham Realty is a 27-unit project in Vile Parle West, Mumbai 400056, launched in August 2023 with possession due in December 2026. 13 units booked out of 14 units for sale. The concrete structure (RCC) is complete.
Read full summary
Meera Kunj is a project by Arham Realty in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800052395. It was launched in August 2023. It has 27 units in 1 building: 23 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 14 are for sale and 13 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
13 units booked out of 14 units for sale (93%).