Sale Building 1 - Chamunda Crown And Sale Building 3 - Chamunda Classic, Vile Parle East
Ready to move
by Chamunda Builders & Developers · Vile Parle East, Mumbai 400057 · Map
- Launched
- Sep 20233 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked
- 61 of 9465% · 51 in Jul 2026
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 31
- 2 BHK
- 63
- Total units
- 94
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 61 | |
| 100% | 100% | 100% | 51 | |
| 100% | 100% | 95% | 47 | |
| 100% | 100% | 5% | 21 |
"–" means MahaRERA shows no figure for that update.
About this project
Sale Building 1 - Chamunda Crown And Sale Building 3 - Chamunda Classic by Chamunda Builders & Developers is a 94-unit SRA-sanctioned project in Vile Parle East, Mumbai 400057, launched in September 2023 with possession due in December 2026. 61 units booked out of total 94 units. The concrete structure (RCC) is complete.
Read full summary
Sale Building 1 - Chamunda Crown And Sale Building 3 - Chamunda Classic is an SRA-sanctioned project by Chamunda Builders & Developers in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800052456. It was launched in September 2023. It has 94 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
61 units booked out of total 94 units (65%). Since the July 2026 update, 10 more units have been booked.