Sai Kutir Ressidency, Vikhroli

by Om Sai Sss Developers Thane · Vikhroli, Mumbai 400083 · Map

Launched
Sep 20233 yrs 3 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
21
1 BHK
330
2 BHK
3
Other units
6
Total units
360
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400083

Projects with 150–800 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths3 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2026Dec 2027
Concrete structure (RCC)0%46%
MahaRERA complaints (filed by or against the builder)11

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sai Kutir Ressidency by Om Sai Sss Developers Thane is a 360-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in September 2023 with possession due in December 2026. Work on the concrete structure (RCC) has not started.

Read full summary

Sai Kutir Ressidency is a MHADA-sanctioned project by Om Sai Sss Developers Thane in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800052499. It was launched in September 2023. It has 360 units in 1 building: 354 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.