Skip to main content

EMPRESS HILL A B C and D Wings, Powai

by HGP Community Pvt Ltd · Powai, Mumbai 400076 · Map

Launched
Sep 20235 yrs 3 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
91%Mid-construction
Booked
337 of 35994% · 327 in Jul 2026
Buildings
10.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
6
3 BHK
309
4 BHK
44
Total units
359
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)91%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 27%Dec 2025: Concrete structure (RCC) 91%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 91%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 91%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%91%0%337
100%91%0%327
100%91%0%300
100%27%0%249

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

EMPRESS HILL A B C and D Wings by HGP Community Pvt Ltd is a 359-unit BMC-sanctioned project in Powai, Mumbai 400076, launched in September 2023 with possession due in December 2028. 337 units booked out of total 359 units. The concrete structure (RCC) is 91% complete.

Read full summary

EMPRESS HILL A B C and D Wings is a BMC-sanctioned project by HGP Community Pvt Ltd in Powai, Mumbai 400076, registered with MahaRERA as P51800052633. It was launched in September 2023. It has 359 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 91% complete, final finishes not started.

337 units booked out of total 359 units (94%). Since the July 2026 update, 10 more units have been booked.

HGP Community's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA9
Total units across these projects2,923
Completed without extending the possession date7
Completed after an extension0
Lapsed0
Under construction2
Possession date extended on the builder's application0
Typical time from launch to 100% structure7 years 5 months
MahaRERA complaints (filed by or against the builder), all HGP Community projects11 (5 of 9 projects)

See all HGP Community projects →