Parshwa Darshan Co Operative Housing Society Limited, Vile Parle West
by Svecha Realty LLP · Vile Parle West, Mumbai 400056 · Map
- Launched
- Sep 20231 yr 3 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 3 yrs
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 8 of 1747% · 21 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 17 units
Rehab21 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 4
- 2 BHK
- 20
- 3 BHK
- 4
- Other units
- 10
- Total units
- 38
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 17
- Rehab units
- 21
- Reserved units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 10% | 8 | |
| 100% | 80% | 10% | 8 | |
| 100% | 88% | 0% | – | |
| 100% | 11% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Parshwa Darshan Co Operative Housing Society Limited by Svecha Realty LLP is a 38-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in September 2023 with possession due in December 2027. 8 units booked out of 17 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Parshwa Darshan Co Operative Housing Society Limited is a BMC-sanctioned project by Svecha Realty LLP in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800052656. It was launched in September 2023. It has 38 units in 1 building: 28 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 17 are for sale and 21 are rehab units for existing members.
Its registered possession date is December 2027, extended by 3 years from the original December 2024. Construction: excavation complete, structure (RCC) 80% complete, final finishes 10% complete.
8 units booked out of 17 units for sale (47%).