Sona Heights, Chandivali

by Sumukha Realtors & Developers · Chandivali, Mumbai 400072 · Map

Launched
Oct 20233 yrs 9 mths promised
Possession (MahaRERA)
Jul 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
0 of 150%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 15 units

Land-owner share9 units, not for sale

Total 24 units. Land-owner units are not for sale.

Project facts

1 BHK
8
2 BHK
14
Other units
2
Total units
24
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Land-owner share (not for sale)
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%0
100%100%0%0
100%70%0%–
100%70%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sona Heights by Sumukha Realtors & Developers is a 24-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in October 2023 with possession due in July 2027. 0 units booked out of 15 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sona Heights is a BMC-sanctioned project by Sumukha Realtors & Developers in Chandivali, Mumbai 400072, registered with MahaRERA as P51800052881. It was launched in October 2023. It has 24 units in 1 building: 22 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 15 are for sale and 9 are the land-owner's share, not for sale.

Its registered possession date is July 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

0 units booked out of 15 units for sale (0%).