SUPREMO PHASE II, WING C known as SAKURA, Mulund East
by K V Buildhome LLP · Mulund East, Mumbai 400081 · Map
- Launched
- Oct 20237 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 49%Mid-construction
- Booked
- 229 of 31672% · 223 in Jul 2026
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 199
- 2 BHK
- 117
- Total units
- 316
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 49% | 1% | 229 | |
| 100% | 49% | 1% | 223 | |
| 100% | 37% | 0% | 205 | |
| 100% | 11% | 0% | 156 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400081
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 2 mths | 5 yrs 4 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2030 | Dec 2028 |
| Concrete structure (RCC) | 49% | 28% |
| Units booked | 72% | 62% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Ganesh Dham, Mulund East
- Jaydeep Icon, Mulund East
- Avneesh Imperium, Mulund East
- Senroofs Phase IV, Building No D1, Wing A Known As Solana, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ganesh Dham | November 2023 | December 2029 | 40% | 29 units booked out of 78 units for sale |
| Jaydeep Icon | November 2023 | March 2027 | 95% | 74 units booked out of total 158 units |
| Avneesh Imperium | May 2023 | December 2027 | 0% | 162 units booked out of 183 units for sale |
| Senroofs Phase IV, Building No D1, Wing A Known As Solana | April 2024 | December 2030 | 17% | 225 units booked out of total 291 units |
About this project
SUPREMO PHASE II, WING C known as SAKURA by K V Buildhome LLP is a 316-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in October 2023 with possession due in December 2030. 229 units booked out of total 316 units. The concrete structure (RCC) is 49% complete.
Read full summary
SUPREMO PHASE II, WING C known as SAKURA is a BMC-sanctioned project by K V Buildhome LLP in Mulund East, Mumbai 400081, registered with MahaRERA as P51800052921. It was launched in October 2023. It has 316 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 49% complete, final finishes 1% complete.
229 units booked out of total 316 units (72%). Since the July 2026 update, 6 more units have been booked.