Proposed Red. On Plot Bearing Fp No.41H Of Tps III Village Kanheri At Borivali East Mumbai, Borivali East

by Mitesh B Shah · Borivali East, Mumbai 400066 · Map

Launched
Oct 20231 yr 7 mths originally promised
Possession (MahaRERA)
Sep 2027Extended by 2 yrs 4 mths
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%–
100%100%60%–
100%100%60%–
100%100%20%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Proposed Red. On Plot Bearing Fp No.41H Of Tps III Village Kanheri At Borivali East Mumbai by Mitesh B Shah is a BMC-sanctioned project in Borivali East, Mumbai 400066, launched in October 2023 with possession due in September 2027. The concrete structure (RCC) is complete.

Read full summary

Proposed Red. On Plot Bearing Fp No.41H Of Tps III Village Kanheri At Borivali East Mumbai is a BMC-sanctioned project by Mitesh B Shah in Borivali East, Mumbai 400066, registered with MahaRERA as P51800053088. It was launched in October 2023. Its MahaRERA status is Active.

Its registered possession date is September 2027, extended by 2 years 4 months from the original May 2025. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.