Redevlopement of SBI Madhur Milan CHSL, Ghatkopar West
by Heritage Lifestyles and Developers Pvt Ltd · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Oct 20232 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr 7 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 9 of 1850% · 26 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 18 units
Rehab26 units for existing members
Total 44 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 10
- 3 BHK
- 34
- Total units
- 44
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 26
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 9 | |
| 100% | 100% | 30% | 9 | |
| 100% | 80% | 0% | 4 | |
| 100% | 70% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Redevlopement of SBI Madhur Milan CHSL by Heritage Lifestyles and Developers Pvt Ltd is a 44-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in October 2023 with possession due in December 2027. 9 units booked out of 18 units for sale. The concrete structure (RCC) is complete.
Read full summary
Redevlopement of SBI Madhur Milan CHSL is a BMC-sanctioned project by Heritage Lifestyles and Developers Pvt Ltd in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800053113. It was launched in October 2023. It has 44 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 18 are for sale and 26 are rehab units for existing members.
Its registered possession date is December 2027, extended by 1 year 7 months from the original May 2026. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.
9 units booked out of 18 units for sale (50%).