Skip to main content

Redevlopement of SBI Madhur Milan CHSL, Ghatkopar West

by Heritage Lifestyles and Developers Pvt Ltd · Ghatkopar West, Mumbai 400086 · Map

Launched
Oct 20232 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 1 yr 7 mths
Concrete structure
100%Nearing possession
Booked (free sale)
9 of 1850% · 26 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale9 booked out of 18 units

Rehab26 units for existing members

Total 44 units. Rehab units are not for sale.

Project facts

2 BHK
10
3 BHK
34
Total units
44
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
18
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%9
100%100%30%9
100%80%0%4
100%70%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Redevlopement of SBI Madhur Milan CHSL by Heritage Lifestyles and Developers Pvt Ltd is a 44-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in October 2023 with possession due in December 2027. 9 units booked out of 18 units for sale. The concrete structure (RCC) is complete.

Read full summary

Redevlopement of SBI Madhur Milan CHSL is a BMC-sanctioned project by Heritage Lifestyles and Developers Pvt Ltd in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800053113. It was launched in October 2023. It has 44 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 18 are for sale and 26 are rehab units for existing members.

Its registered possession date is December 2027, extended by 1 year 7 months from the original May 2026. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

9 units booked out of 18 units for sale (50%).