Skip to main content

Avira Jewellery Hub, Malad West

by Avira Realty Private Limited · Malad West, Mumbai 400064 · Map

Launched
Oct 20233 yrs 11 mths promised
Possession (MahaRERA)
Sep 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
53 of 14537% · 92 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale53 booked out of 145 units

Rehab92 units for existing members

Total 237 units. Rehab units are not for sale.

Project facts

Other units
237
Total units
237
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
145
Rehab units
92

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 20%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%53
100%100%0%47
100%20%0%42
100%20%0%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Avira Jewellery Hub by Avira Realty Private Limited is a 237-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in October 2023 with possession due in September 2027. 53 units booked out of 145 units for sale. The concrete structure (RCC) is complete.

Read full summary

Avira Jewellery Hub is a BMC-sanctioned project by Avira Realty Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800053369. It was launched in October 2023. It has 237 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 237 units, 145 are for sale and 92 are rehab units for existing members.

Its registered possession date is September 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

53 units booked out of 145 units for sale (37%). Since the July 2026 update, 6 more units have been booked.