Crest Oaks, Andheri East

by Hill View Developers · Andheri East, Mumbai 400059 · Map

Launched
Oct 20234 yrs 2 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked
97 of 12975% · 87 in Jul 2026
Buildings
31 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
105
3 BHK
14
4 BHK
10
Total units
129
Buildings
3
Land
1 acre
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 58%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 42%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%97
100%100%42%87
100%58%0%56
100%0%0%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Crest Oaks by Hill View Developers is a 129-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in October 2023 with possession due in December 2027. 97 units booked out of total 129 units. The concrete structure (RCC) is complete.

Read full summary

Crest Oaks is a BMC-sanctioned project by Hill View Developers in Andheri East, Mumbai 400059, registered with MahaRERA as P51800053387. It was launched in October 2023. It has 129 units in 3 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

97 units booked out of total 129 units (75%). Since the July 2026 update, 10 more units have been booked.