Avalon Residency, Goregaon West
by Avalon Residency LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- Oct 2023First of 2 phases
- Possession (MahaRERA)
- May 2028 – Dec 2028Not extended
- Concrete structure
- 98%Weighted across 2 phases
- Booked (free sale)
- 33 of 6650% · 107 rehab units
- Buildings
- 21.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale33 booked out of 66 units
Rehab107 units for existing members
Total 173 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 27
- 2 BHK
- 129
- Other units
- 17
- Total units
- 173
- Buildings
- 2
- Land
- 1.2 acres
- Phases
- 2
- MahaRERA complaints
- 0
- Free-sale units
- 66
- Rehab units
- 107
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Avalon Residency Nearing possession | P51800053429 | 156 | 100% | 20% | |
| Avalon Residency Tower 1 Early stage | P51800081096 | 0 | 0% | 0% |
Show updates by phase
Avalon Residency (P51800053429)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 33 | |
| 100% | 100% | 0% | 32 | |
| 100% | 100% | 0% | 25 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Avalon Residency Tower 1 (P51800081096)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 0 | |
| 80% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Avalon Residency by Avalon Residency LLP is a 173-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, registered with MahaRERA in 2 phases, with possession dates from May 2028 to December 2028. 33 units booked out of 66 units for sale. The concrete structure (RCC) is 98% complete.
Read full summary
Avalon Residency is a BMC-sanctioned project by Avalon Residency LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as 2 phases (P51800053429, P51800081096). The first phase was launched in October 2023. Together the phases have 173 units in 2 buildings: 156 homes (1 and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 173 units, 66 are for sale and 107 are rehab units for existing members.
The phases' registered possession dates run from May 2028 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 98% complete and final finishes 0% complete. Neither phase has its structure complete.
33 units booked out of 66 units for sale (50%). Since the July 2026 update, 1 more unit has been booked.