Gyan Gold Crest, Jogeshwari East
by Gyan S. P. Developers LLP · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Dec 20234 yrs promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 3%Mid-construction
- Booked (free sale)
- 411 of 45990%
- Buildings
- 23 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale411 booked out of 459 units
Land-owner share37 units, not for sale
Total 496 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 478
- 3 BHK
- 1
- 5+ BHK
- 1
- Other units
- 16
- Total units
- 496
- Buildings
- 2
- Land
- 3 acres
- Phases
- 1
- MahaRERA complaints
- 6
- Reserved units
- 246
- Free-sale units
- 459
- Land-owner share (not for sale)
- 37
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 3% | 0% | 411 | |
| 100% | 0% | 0% | 410 | |
| 100% | 0% | 0% | 79 | |
| 100% | 0% | 0% | 50 |
"–" means MahaRERA shows no figure for that update.
About this project
Gyan Gold Crest by Gyan S. P. Developers LLP is a 496-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in December 2023 with possession due in December 2027. 411 units booked out of 459 units for sale. The concrete structure (RCC) is 3% complete.
Read full summary
Gyan Gold Crest is an SRA-sanctioned project by Gyan S. P. Developers LLP in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800053907. It was launched in December 2023. It has 496 units in 2 buildings: 480 homes (1, 3 and 5+ BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 496 units, 459 are for sale and 37 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 3% complete, final finishes not started.
411 units booked out of 459 units for sale (90%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 0% to 3%.