9 Bkc, Santacruz East
by Resham Singh Developers LLP · Santacruz East, Mumbai 400098 · Map
- Launched
- Dec 20233 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 0%Early stage
- Booked
- 9 of 1416% · 0 in Jul 2026
- Buildings
- 21.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 22
- Other units
- 119
- Total units
- 141
- Buildings
- 2
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 75% | 0% | 0% | 9 | |
| 75% | 0% | 0% | 0 | |
| 75% | 0% | 0% | 0 | |
| 75% | 0% | 0% | 9 |
"–" means MahaRERA shows no figure for that update.
About this project
9 Bkc by Resham Singh Developers LLP is a 141-unit BMC-sanctioned project in Santacruz East, Mumbai 400098, launched in December 2023 with possession due in December 2026. 9 units booked out of total 141 units. Work on the concrete structure (RCC) has not started.
Read full summary
9 Bkc is a BMC-sanctioned project by Resham Singh Developers LLP in Santacruz East, Mumbai 400098, registered with MahaRERA as P51800054080. It was launched in December 2023. It has 141 units in 2 buildings: 22 homes (1 BHK) and 119 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation 75% complete, structure (RCC) not started, final finishes not started.
9 units booked out of total 141 units (6%). Since the July 2026 update, 9 more units have been booked.