Sai Jyoti, Khar West
by Shambhavi Enterprises · Khar West, Mumbai 400052 · Map
- Launched
- Dec 20233 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 4 of 944% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 9 units
Rehab8 units for existing members
Total 17 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 9
- 4 BHK
- 7
- Total units
- 17
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | 4 | |
| 100% | 100% | 0% | 2 | |
| 100% | 80% | 0% | 1 | |
| 100% | 22% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400052
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 3 yrs 2 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 44% | 75% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Searock Residences, Khar West
- Wild Teasel, Khar West
- Evaana, Khar West
- KK Elegance, Khar West
- New Shelter Co Op Housing Society Ltd, Khar West
- 259 Park Crest, Khar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Searock Residences | October 2023 | October 2026 | 0% | 3 units booked out of 15 units for sale |
| Wild Teasel | February 2024 | September 2027 | 100% | 12 units booked out of 16 units for sale |
| Evaana | October 2023 | April 2027 | 100% | 12 units booked out of 16 units for sale |
| KK Elegance | September 2023 | December 2026 | 100% | 9 units booked out of 10 units for sale |
| New Shelter Co Op Housing Society Ltd | September 2023 | December 2025 | 0% | 6 units booked out of total 8 units |
| 259 Park Crest | May 2024 | December 2026 | 100% | – |
About this project
Sai Jyoti by Shambhavi Enterprises is a 17-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in December 2023 with possession due in December 2026. 4 units booked out of 9 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sai Jyoti is a BMC-sanctioned project by Shambhavi Enterprises in Khar West, Mumbai 400052, registered with MahaRERA as P51800054144. It was launched in December 2023. It has 17 units in 1 building, with 1, 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 17 units, 9 are for sale and 8 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.
4 units booked out of 9 units for sale (44%). Since the July 2026 update, 2 more units have been booked.