Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - C, Malad West
by Shreeji Construction · Malad West, Mumbai 400064 · Map
- Launched
- Jan 20243 yrs 5 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 71%Mid-construction
- Booked (free sale)
- 94 of 11880% · 79 rehab units
- Buildings
- 30.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale94 booked out of 118 units
Rehab79 units for existing members
Total 197 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 18
- 2 BHK
- 154
- 3 BHK
- 1
- Other units
- 24
- Total units
- 197
- Buildings
- 3
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 118
- Rehab units
- 79
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 71% | 0% | 94 | |
| 100% | 31% | 0% | 86 | |
| 100% | 0% | 0% | 68 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400064
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 3 yrs 10 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Jun 2027 | Dec 2029 |
| Concrete structure (RCC) | 71% | 100% |
| Units booked (free sale) | 80% | 46% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Narang Vivenda, Malad West
- Kamla Ridhima, Malad West
- Building No 2 Ajmera Shikhar, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Narang Vivenda | April 2024 | December 2029 | 100% | 165 units booked out of total 254 units |
| Kamla Ridhima | September 2023 | May 2027 | 100% | 31 units booked out of 68 units for sale |
| Building No 2 Ajmera Shikhar | September 2023 | December 2030 | 0% | 10 units booked out of 161 units for sale |
About this project
Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - C by Shreeji Construction is a 197-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in January 2024 with possession due in June 2027. 94 units booked out of 118 units for sale. The concrete structure (RCC) is 71% complete.
Read full summary
Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - C is an SRA-sanctioned project by Shreeji Construction in Malad West, Mumbai 400064, registered with MahaRERA as P51800054310. It was launched in January 2024. It has 197 units in 3 buildings: 173 homes (1, 2 and 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 197 units, 118 are for sale and 79 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 71% complete, final finishes not started.
94 units booked out of 118 units for sale (80%). Since the July 2026 update, 8 more units have been booked and the reported concrete structure (RCC) has gone from 31% to 71%.