Nebula Empress, Khar West
by M/s Shiv Sai developer · Khar West, Mumbai 400052 · Map
- Launched
- Jan 20243 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 82%Mid-construction
- Booked (free sale)
- 87 of 87100%
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale87 booked out of 87 units
Land-owner share25 units, not for sale
Total 112 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 109
- Other units
- 3
- Total units
- 112
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 87
- Free-sale units
- 87
- Land-owner share (not for sale)
- 25
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 82% | 77% | 87 | |
| 100% | 82% | 77% | 87 | |
| 100% | 82% | 77% | 87 | |
| 100% | 100% | 95% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Nebula Empress by M/s Shiv Sai developer is a 112-unit SRA-sanctioned project in Khar West, Mumbai 400052, launched in January 2024 with possession due in December 2027. 87 units booked out of 87 units for sale. The concrete structure (RCC) is 82% complete.
Read full summary
Nebula Empress is an SRA-sanctioned project by M/s Shiv Sai developer in Khar West, Mumbai 400052, registered with MahaRERA as P51800054371. It was launched in January 2024. It has 112 units in 2 buildings: 109 homes (1 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 112 units, 87 are for sale and 25 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 82% complete, final finishes 77% complete.
87 units booked out of 87 units for sale (100%).