Aaradhya Onepark, Ghatkopar East
by Micl Creators LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Jan 20244 yrs 6 mths promised
- Possession (MahaRERA)
- Jul 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 131 of 24653% · 222 rehab units
- Buildings
- 113.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale131 booked out of 246 units
Rehab222 units for existing members
Total 468 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 29
- 3 BHK
- 315
- 4 BHK
- 121
- 5+ BHK
- 3
- Total units
- 468
- Buildings
- 11
- Land
- 3.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 246
- Rehab units
- 222
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 78% | 131 | |
| 100% | 96% | 26% | 121 | |
| 100% | 49% | 0% | 112 | |
| 86% | 0% | 0% | 89 |
"–" means MahaRERA shows no figure for that update.
About this project
Aaradhya Onepark by Micl Creators LLP is a 468-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in January 2024 with possession due in July 2028. 131 units booked out of 246 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aaradhya Onepark is a BMC-sanctioned project by Micl Creators LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800054477. It was launched in January 2024. It has 468 units in 11 buildings, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 468 units, 246 are for sale and 222 are rehab units for existing members.
Its registered possession date is July 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 78% complete.
131 units booked out of 246 units for sale (53%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 96% to 100%.