Mangal Business Park - Gautam Apartment, Malad West

by Mangal Buildhome Private Limited · Malad West, Mumbai 400064 · Map

Launched
Feb 20243 yrs 1 mth promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
199 of 20299% · 76 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale199 booked out of 202 units

Rehab76 units for existing members

Total 278 units. Rehab units are not for sale.

Project facts

Other units
278
Total units
278
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
202
Rehab units
76

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 20%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%199
100%100%20%197
100%40%0%202
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mangal Business Park - Gautam Apartment by Mangal Buildhome Private Limited is a 278-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in February 2024 with possession due in March 2027. 199 units booked out of 202 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mangal Business Park - Gautam Apartment is a BMC-sanctioned project by Mangal Buildhome Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800054656. It was launched in February 2024. It has 278 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 278 units, 202 are for sale and 76 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

199 units booked out of 202 units for sale (99%). Since the July 2026 update, 2 more units have been booked.