Mangal Business Park - Gautam Apartment, Malad West
by Mangal Buildhome Private Limited · Malad West, Mumbai 400064 · Map
- Launched
- Feb 20243 yrs 1 mth promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 199 of 20299% · 76 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale199 booked out of 202 units
Rehab76 units for existing members
Total 278 units. Rehab units are not for sale.
Project facts
- Other units
- 278
- Total units
- 278
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 202
- Rehab units
- 76
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 199 | |
| 100% | 100% | 20% | 197 | |
| 100% | 40% | 0% | 202 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Mangal Business Park - Gautam Apartment by Mangal Buildhome Private Limited is a 278-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in February 2024 with possession due in March 2027. 199 units booked out of 202 units for sale. The concrete structure (RCC) is complete.
Read full summary
Mangal Business Park - Gautam Apartment is a BMC-sanctioned project by Mangal Buildhome Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800054656. It was launched in February 2024. It has 278 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 278 units, 202 are for sale and 76 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
199 units booked out of 202 units for sale (99%). Since the July 2026 update, 2 more units have been booked.