The Address by GS Bandra, Bandra East

by TEN X Realty Limited · Bandra East, Mumbai 400051 · Map

Launched
Feb 2024First of 8 phases
Possession (MahaRERA)
Jan 2030 – Jun 2031Not extended
Concrete structure
6%Weighted across 8 phases
Booked
512 of 80264% · 434 in Jul 2026
Buildings
83.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
525
3 BHK
197
4 BHK
69
Other units
10
Total units
802
Buildings
8
Land
3.4 acres
Phases
8
MahaRERA complaints
1

The 8 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
The Address by GS Bandra Tower C
Mid-construction
P518000548289013%83%
The Address by GS Bandra Tower B
Mid-construction
P518000548468913%81%
The Address by GS Bandra Tower A
Mid-construction
P518000548478826%74%
The Address by GS Bandra Tower D
Early stage
P518000664571320%42%
The Address by GS Bandra Tower E
Early stage
P51800078863880%86%
The Address by GS Bandra Tower F
Early stage
P518000789221080%67%
The Address by GS Bandra Tower H
Early stage
PR1180002502783650%0%
The Address by GS Bandra Tower G
Early stage
PR11800025027951320%67%
Show updates by phase

The Address by GS Bandra Tower C (P51800054828)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%13%0%75
100%0%0%76
100%0%0%73
50%0%0%0

"–" means MahaRERA shows no figure for that update.

The Address by GS Bandra Tower B (P51800054846)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%13%0%77
100%0%0%78
100%0%0%71
30%0%0%0

"–" means MahaRERA shows no figure for that update.

The Address by GS Bandra Tower A (P51800054847)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%26%0%68
100%0%0%63
100%0%0%52
31%0%0%0

"–" means MahaRERA shows no figure for that update.

The Address by GS Bandra Tower D (P51800066457)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%56
60%0%0%51
45%0%0%42
30%0%0%0

"–" means MahaRERA shows no figure for that update.

The Address by GS Bandra Tower E (P51800078863)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%76
0%0%0%72
0%0%0%62
0%0%0%0

"–" means MahaRERA shows no figure for that update.

The Address by GS Bandra Tower F (P51800078922)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%72
0%0%0%73
0%0%0%32
0%0%0%0

"–" means MahaRERA shows no figure for that update.

The Address by GS Bandra Tower H (PR1180002502783)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

The Address by GS Bandra Tower G (PR1180002502795)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%88
0%0%0%21

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)6%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 44%Oct 2026: Excavation 50%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 6%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 6%Final finishes 0%

How to read construction stages

About this project

The Address by GS Bandra by TEN X Realty Limited is an 802-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, registered with MahaRERA in 8 phases, with possession dates from January 2030 to June 2031. 512 units booked out of total 802 units. The concrete structure (RCC) is 6% complete.

Read full summary

The Address by GS Bandra is a MHADA-sanctioned project by TEN X Realty Limited in Bandra East, Mumbai 400051, registered with MahaRERA as 8 phases (P51800054828, P51800054846, P51800054847, P51800066457, P51800078863, P51800078922, PR1180002502783, PR1180002502795). The first phase was launched in February 2024. Together the phases have 802 units in 8 buildings: 792 homes (1, 2, 3 and 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. All 8 phases are active on MahaRERA.

The phases' registered possession dates run from January 2030 to June 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 6% complete and final finishes 0% complete. None of the 8 phases has its structure complete.

512 units booked out of total 802 units (64%). Since the July 2026 update, 78 more units have been booked.

Ten X Realty's track record in Mumbai

MahaRERA projects registered 2024–2026 in Mumbai

Projects registered with MahaRERA23
Total units across these projects2,581
Completed without extending the possession date0
Completed after an extension0
Lapsed0
Under construction23
Possession date extended on the builder's application0
MahaRERA complaints (filed by or against the builder), all Ten X Realty projects2 (2 of 23 projects)

See all Ten X Realty projects →