Elysium, Chembur
by Kripa Elite Homes · Chembur, Mumbai 400089 · Map
- Launched
- Feb 20243 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 154 of 16096%
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale154 booked out of 160 units
Land-owner share40 units, not for sale
Total 200 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 94
- 2 BHK
- 82
- Other units
- 24
- Total units
- 200
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 160
- Land-owner share (not for sale)
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | 154 | |
| 100% | 100% | 20% | 146 | |
| 100% | 75% | 0% | 114 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Elysium by Kripa Elite Homes is a 200-unit MHADA-sanctioned project in Chembur, Mumbai 400089, launched in February 2024 with possession due in December 2027. 154 units booked out of 160 units for sale. The concrete structure (RCC) is complete.
Read full summary
Elysium is a MHADA-sanctioned project by Kripa Elite Homes in Chembur, Mumbai 400089, registered with MahaRERA as P51800054981. It was launched in February 2024. It has 200 units in 2 buildings: 176 homes (1 and 2 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 200 units, 160 are for sale and 40 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.
154 units booked out of 160 units for sale (96%). Since the July 2026 update, 8 more units have been booked.