Modi Arcade, Kandivali West

by Rajendra Jethalal Modi · Kandivali West, Mumbai 400067 · Map

Launched
Feb 20245 yrs 7 mths promised
Possession (MahaRERA)
Sep 2029Not extended
Concrete structure
35%Mid-construction
Booked (free sale)
25 of 7533% · 24 rehab units
Buildings
10.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 75 units

Rehab24 units for existing members

Total 99 units. Rehab units are not for sale.

Project facts

Other units
99
Total units
99
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
1
Free-sale units
75
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 35%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 35%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%10%25
100%5%0%23
100%5%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Modi Arcade by Rajendra Jethalal Modi is a 99-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in February 2024 with possession due in September 2029. 25 units booked out of 75 units for sale. The concrete structure (RCC) is 35% complete.

Read full summary

Modi Arcade is a BMC-sanctioned project by Rajendra Jethalal Modi in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800054984. It was launched in February 2024. It has 99 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 99 units, 75 are for sale and 24 are rehab units for existing members.

Its registered possession date is September 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes 10% complete.

25 units booked out of 75 units for sale (33%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 5% to 35%.