Omtech VKW Business Tower, Vikhroli

by Omtech Enterprises · Vikhroli, Mumbai 400079 · Map

Launched
Mar 20243 yrs promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation60%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 60%Jul 2026: Excavation 60%Oct 2026: Excavation 60%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 60%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
60%0%0%–
60%0%0%–
60%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Omtech VKW Business Tower by Omtech Enterprises is a BMC-sanctioned project in Vikhroli, Mumbai 400079, launched in March 2024 with possession due in March 2027. Work on the concrete structure (RCC) has not started.

Read full summary

Omtech VKW Business Tower is a BMC-sanctioned project by Omtech Enterprises in Vikhroli, Mumbai 400079, registered with MahaRERA as P51800055214. It was launched in March 2024. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation 60% complete, structure (RCC) not started, final finishes not started.