Skip to main content

Sree Sudarshan Heights, Chembur

by Aum Sai Constructions Private Limited · Chembur, Mumbai 400089 · Map

Launched
Mar 20242 yrs 9 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
8 of 2829% · 19 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 28 units

Rehab19 units for existing members

Total 47 units. Rehab units are not for sale.

Project facts

1 RK
11
1 BHK
11
2 BHK
10
3 BHK
15
Total units
47
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%8
100%100%0%8
100%0%0%8
100%0%0%27

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sree Sudarshan Heights by Aum Sai Constructions Private Limited is a 47-unit BMC-sanctioned project in Chembur, Mumbai 400089, launched in March 2024 with possession due in December 2026. 8 units booked out of 28 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sree Sudarshan Heights is a BMC-sanctioned project by Aum Sai Constructions Private Limited in Chembur, Mumbai 400089, registered with MahaRERA as P51800055263. It was launched in March 2024. It has 47 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 28 are for sale and 19 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

8 units booked out of 28 units for sale (29%).