Ampple-One, Chembur

Ready to move

by Amppletech Projects Private Limited · Chembur, Mumbai 400089 · Map

Launched
Mar 20242 yrs 3 mths originally promised
Possession (MahaRERA)
Mar 2027Extended by 9 mths
Concrete structure
100%Ready to move
Booked (free sale)
19 of 2095% · 19 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale19 booked out of 20 units

Rehab19 units for existing members

Total 39 units. Rehab units are not for sale.

Project facts

1 BHK
10
2 BHK
19
3 BHK
10
Total units
39
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
20
Rehab units
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 35%Dec 2025: Concrete structure (RCC) 35%Jul 2026: Concrete structure (RCC) 35%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%19
100%35%0%13
100%35%0%13
100%35%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ampple-One by Amppletech Projects Private Limited is a 39-unit BMC-sanctioned project in Chembur, Mumbai 400089, launched in March 2024 with possession due in March 2027. 19 units booked out of 20 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ampple-One is a BMC-sanctioned project by Amppletech Projects Private Limited in Chembur, Mumbai 400089, registered with MahaRERA as P51800055324. It was launched in March 2024. It has 39 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 39 units, 20 are for sale and 19 are rehab units for existing members.

Its registered possession date is March 2027, extended by 9 months from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

19 units booked out of 20 units for sale (95%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 35% to 100%.