78 Lake Town, Andheri West
by Anirdesh Developers Private Limited · Andheri West, Mumbai 400053 · Map
- Launched
- Mar 20244 yrs 11 mths promised
- Possession (MahaRERA)
- Feb 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 378 of 41691%
- Buildings
- 16.8 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale378 booked out of 416 units
Land-owner share21 units, not for sale
Total 437 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 436
- Other units
- 1
- Total units
- 437
- Buildings
- 1
- Land
- 6.8 acres
- Phases
- 1
- MahaRERA complaints
- 6
- Free-sale units
- 416
- Land-owner share (not for sale)
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 75% | 0% | 0% | 378 | |
| 75% | 0% | 0% | 343 | |
| 70% | 0% | 0% | 343 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
78 Lake Town by Anirdesh Developers Private Limited is a 437-unit SRA-sanctioned project in Andheri West, Mumbai 400053, launched in March 2024 with possession due in February 2029. 378 units booked out of 416 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
78 Lake Town is an SRA-sanctioned project by Anirdesh Developers Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800055387. It was launched in March 2024. It has 437 units in 1 building: 436 homes (1 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 437 units, 416 are for sale and 21 are the land-owner's share, not for sale.
Its registered possession date is February 2029, unchanged since launch. Construction: excavation 75% complete, structure (RCC) not started, final finishes not started.
378 units booked out of 416 units for sale (91%). Since the July 2026 update, 35 more units have been booked.