Raj One, Kandivali West
by Raj Realtors · Kandivali West, Mumbai 400067 · Map
- Launched
- Mar 20243 yrs 5 mths promised
- Possession (MahaRERA)
- Aug 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 153 of 16692%
- Buildings
- 20.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale153 booked out of 166 units
Land-owner share4 units, not for sale
Total 170 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 56
- 2 BHK
- 53
- 3 BHK
- 49
- Other units
- 12
- Total units
- 170
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Reserved units
- 31
- Free-sale units
- 166
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 25% | 153 | |
| 100% | 95% | 0% | 134 | |
| 100% | 45% | 0% | 99 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400067
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 3 yrs 7 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Aug 2027 | Dec 2027 |
| Concrete structure (RCC) | 100% | 56% |
| Units booked (free sale) | 92% | 34% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Soham Heights, Kandivali West
- Shreyaan Heights, Kandivali West
- Vasupujya Darshan, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Soham Heights | May 2024 | December 2027 | 56% | 68 units booked out of total 153 units |
| Shreyaan Heights | May 2024 | April 2031 | 36% | 30 units booked out of 144 units for sale |
| Vasupujya Darshan | December 2023 | December 2026 | 100% | 14 units booked out of 41 units for sale |
About this project
Raj One by Raj Realtors is a 170-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2024 with possession due in August 2027. 153 units booked out of 166 units for sale. The concrete structure (RCC) is complete.
Read full summary
Raj One is a BMC-sanctioned project by Raj Realtors in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800055404. It was launched in March 2024. It has 170 units in 2 buildings: 158 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 170 units, 166 are for sale and 4 are the land-owner's share, not for sale.
Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.
153 units booked out of 166 units for sale (92%). Since the July 2026 update, 19 more units have been booked and the reported concrete structure (RCC) has gone from 95% to 100%.