Sayba Olympia, Kurla West

by Star Shine · Kurla West, Mumbai 400070 · Map

Launched
Mar 20242 yrs 9 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
98%Mid-construction
Booked (free sale)
29 of 7439% · 215 rehab units
Buildings
81.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale29 booked out of 74 units

Rehab215 units for existing members

Total 289 units. Rehab units are not for sale.

Project facts

1 BHK
219
2 BHK
70
Total units
289
Buildings
8
Land
1.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
74
Rehab units
215

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services78%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 24%Jul 2026: Excavation 30%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 98%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 78%Excavation 100%Concrete structure (RCC) 98%Final finishes 78%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%78%29
30%0%0%19
24%0%0%2
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sayba Olympia by Star Shine is a 289-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in March 2024 with possession due in December 2026. 29 units booked out of 74 units for sale. The concrete structure (RCC) is 98% complete.

Read full summary

Sayba Olympia is a BMC-sanctioned project by Star Shine in Kurla West, Mumbai 400070, registered with MahaRERA as P51800055430. It was launched in March 2024. It has 289 units in 8 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 289 units, 74 are for sale and 215 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 98% complete, final finishes 78% complete.

29 units booked out of 74 units for sale (39%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 98%.