by Galani Ajwani Developers LLP · Khar West, Mumbai 400052 · Map
- Launched
- Apr 20243 yrs 2 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 95%Mid-construction
- Booked
- 56 of 7377% · 49 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 73
- Total units
- 73
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 50% | 56 | |
| 100% | 68% | 0% | 49 | |
| 100% | 40% | 0% | 30 | |
| 0% | 0% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
About this project
La52 by Galani Ajwani Developers LLP is a 73-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in April 2024 with possession due in June 2027. 56 units booked out of total 73 units. The concrete structure (RCC) is 95% complete.
Read full summary
La52 is a BMC-sanctioned project by Galani Ajwani Developers LLP in Khar West, Mumbai 400052, registered with MahaRERA as P51800055498. It was launched in April 2024. It has 73 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes 50% complete.
56 units booked out of total 73 units (77%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 68% to 95%.