Aksa Tower, Jogeshwari West

Ready to move

by Hfi Industries · Jogeshwari West, Mumbai 400102 · Map

Launched
Apr 202411 mths originally promised
Possession (MahaRERA)
Jan 2027Extended by 1 yr 10 mths
Concrete structure
100%Ready to move
Booked
21 of 6532% · 15 in Jul 2026
Buildings
11.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
64
4 BHK
1
Total units
65
Buildings
1
Land
1.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 60%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%21
100%100%100%15
100%100%60%14
100%100%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400102

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)11 mths3 yrs 4 mths
Possession date extendedBy 1 yr 10 mths0 of 3
Possession date (MahaRERA)Jan 2027Mar 2028
Concrete structure (RCC)100%55%
Units booked32%58%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Aksa Tower by Hfi Industries is a 65-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in April 2024 with possession due in January 2027. 21 units booked out of total 65 units. The concrete structure (RCC) is complete.

Read full summary

Aksa Tower is a BMC-sanctioned project by Hfi Industries in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800055503. It was launched in April 2024. It has 65 units in 1 building, with 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is January 2027, extended by 1 year 10 months from the original March 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

21 units booked out of total 65 units (32%). Since the July 2026 update, 6 more units have been booked and the possession date has moved from November 2025 to January 2027.