Hive 97, Malad East
by Amity Constructions · Malad East, Mumbai 400097 · Map
- Launched
- Apr 20245 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 28%Mid-construction
- Booked
- 279 of 57948% · 267 in Jul 2026
- Buildings
- 12.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 579
- Total units
- 579
- Buildings
- 1
- Land
- 2.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 28% | 0% | 279 | |
| 90% | 0% | 0% | 267 | |
| 50% | 0% | 0% | 259 | |
| 25% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Hive 97 by Amity Constructions is a 579-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in April 2024 with possession due in December 2029. 279 units booked out of total 579 units. The concrete structure (RCC) is 28% complete.
Read full summary
Hive 97 is an SRA-sanctioned project by Amity Constructions in Malad East, Mumbai 400097, registered with MahaRERA as P51800055561. It was launched in April 2024. It has 579 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 28% complete, final finishes not started.
279 units booked out of total 579 units (48%). Since the July 2026 update, 12 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 28%.