Zennith, Andheri East
by Apexbliss Infraventures Private Limited · Andheri East, Mumbai 400093 · Map
- Launched
- Apr 20242 yrs 8 mths originally promised
- Possession (MahaRERA)
- Apr 2028Extended by 1 yr 4 mths
- Concrete structure
- 0%Early stage
- Booked
- 124 of 20860% · 93 in Jul 2026
- Buildings
- 10.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 208
- Total units
- 208
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 20% | 124 | |
| 100% | 0% | 15% | 93 | |
| 65% | 0% | 0% | – | |
| 50% | 0% | 0% | 25 |
"–" means MahaRERA shows no figure for that update.
About this project
Zennith by Apexbliss Infraventures Private Limited is a 208-unit project in Andheri East, Mumbai 400093, launched in April 2024 with possession due in April 2028. 124 units booked out of total 208 units. Work on the concrete structure (RCC) has not started.
Read full summary
Zennith is a project by Apexbliss Infraventures Private Limited in Andheri East, Mumbai 400093, registered with MahaRERA as P51800055713. It was launched in April 2024. It has 208 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2028, extended by 1 year 4 months from the original December 2026. Construction: excavation complete, structure (RCC) not started, final finishes 20% complete.
124 units booked out of total 208 units (60%). Since the July 2026 update, 31 more units have been booked and the possession date has moved from December 2026 to April 2028.