Zennith, Andheri East

by Apexbliss Infraventures Private Limited · Andheri East, Mumbai 400093 · Map

Launched
Apr 20242 yrs 8 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 1 yr 4 mths
Concrete structure
0%Early stage
Booked
124 of 20860% · 93 in Jul 2026
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
208
Total units
208
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 65%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 15%Oct 2026: Final finishes 20%Excavation 100%Final finishes 20%Concrete structure (RCC) 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%20%124
100%0%15%93
65%0%0%–
50%0%0%25

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Zennith by Apexbliss Infraventures Private Limited is a 208-unit project in Andheri East, Mumbai 400093, launched in April 2024 with possession due in April 2028. 124 units booked out of total 208 units. Work on the concrete structure (RCC) has not started.

Read full summary

Zennith is a project by Apexbliss Infraventures Private Limited in Andheri East, Mumbai 400093, registered with MahaRERA as P51800055713. It was launched in April 2024. It has 208 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 1 year 4 months from the original December 2026. Construction: excavation complete, structure (RCC) not started, final finishes 20% complete.

124 units booked out of total 208 units (60%). Since the July 2026 update, 31 more units have been booked and the possession date has moved from December 2026 to April 2028.