Skip to main content

Vaidya West World - Harmony, Andheri East

Ready to move

by Vaidya Spaces Private Limited · Andheri East, Mumbai 400069 · Map

Launched
Apr 20243 yrs 3 mths promised
Possession (MahaRERA)
Jul 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
13 of 2357% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 23 units

Rehab12 units for existing members

Total 35 units. Rehab units are not for sale.

Project facts

2 BHK
26
3 BHK
9
Total units
35
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
23
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 8%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%13
100%100%100%13
100%8%0%–
100%8%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vaidya West World - Harmony by Vaidya Spaces Private Limited is a 35-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in April 2024 with possession due in July 2027. 13 units booked out of 23 units for sale. The concrete structure (RCC) is complete.

Read full summary

Vaidya West World - Harmony is a BMC-sanctioned project by Vaidya Spaces Private Limited in Andheri East, Mumbai 400069, registered with MahaRERA as P51800055721. It was launched in April 2024. It has 35 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 23 are for sale and 12 are rehab units for existing members.

Its registered possession date is July 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

13 units booked out of 23 units for sale (57%).