Chandak Highscape City, Chembur
by Chandak Realtors Private Limited · Chembur, Mumbai 400074 · Map
- Launched
- Apr 2024First of 2 phases
- Possession (MahaRERA)
- Dec 2030 – Dec 2032Not extended
- Concrete structure
- 40%Weighted across 2 phases
- Booked
- 236 of 2,05611% · 194 in Jul 2026
- Buildings
- 813.1 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1,022
- 2 BHK
- 668
- 3 BHK
- 331
- Other units
- 35
- Total units
- 2,056
- Buildings
- 8
- Land
- 13.1 acres
- Phases
- 2
- MahaRERA complaints
- 3
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Chandak Highscape City 1A Mid-construction | P51800055726 | 1,148 | 71% | 20% | |
| Chandak Highscape City 1B Early stage | PM1181012400048 | 873 | 0% | 0% |
Show updates by phase
Chandak Highscape City 1A (P51800055726)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 71% | 6% | 236 | |
| 100% | 0% | 0% | 194 | |
| 100% | 0% | 0% | 94 | |
| 100% | 0% | 0% | 75 |
"–" means MahaRERA shows no figure for that update.
Chandak Highscape City 1B (PM1181012400048)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 43% | 0% | 0% | 0 | |
| 43% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Chandak Highscape City by Chandak Realtors Private Limited is a 2,056-unit SRA-sanctioned project in Chembur, Mumbai 400074, registered with MahaRERA in 2 phases, with possession dates from December 2030 to December 2032. 236 units booked out of total 2,056 units. The concrete structure (RCC) is 40% complete.
Read full summary
Chandak Highscape City is an SRA-sanctioned project by Chandak Realtors Private Limited in Chembur, Mumbai 400074, registered with MahaRERA as 2 phases (P51800055726, PM1181012400048). The first phase was launched in April 2024. Together the phases have 2,056 units in 8 buildings: 2,021 homes (1, 2 and 3 BHK) and 35 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from December 2030 to December 2032; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 40% complete and final finishes 3% complete. Neither phase has its structure complete.
236 units booked out of total 2,056 units (11%). Since the July 2026 update, 42 more units have been booked.
Chandak's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 6 |
|---|---|
| Total units across these projects | 3,625 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 5 |
| Possession date extended on the builder's application | 0 |
| MahaRERA complaints (filed by or against the builder), all Chandak projects | 10 (3 of 6 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.