Skip to main content

Vighnaharta Infinity, Vikhroli

by Vighnaharta Heights Private Limited · Vikhroli, Mumbai 400083 · Map

Launched
Apr 20243 yrs 8 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
4%Mid-construction
Booked
8 of 3183%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
150
2 BHK
44
3 BHK
106
Other units
17
Total units
318
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)4%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 4%Oct 2026: Concrete structure (RCC) 4%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 4%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%4%0%8
100%4%0%–
100%0%0%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vighnaharta Infinity by Vighnaharta Heights Private Limited is a 318-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in April 2024 with possession due in December 2027. 8 units booked out of total 318 units. The concrete structure (RCC) is 4% complete.

Read full summary

Vighnaharta Infinity is a MHADA-sanctioned project by Vighnaharta Heights Private Limited in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800055751. It was launched in April 2024. It has 318 units in 1 building: 301 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 4% complete, final finishes not started.

8 units booked out of total 318 units (3%).