Atul Life Phase I, Ghatkopar West
by Atul Projects India Pvt Ltd · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Apr 20246 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 37%Mid-construction
- Booked (free sale)
- 96 of 54618%
- Buildings
- 22.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale96 booked out of 546 units
Land-owner share86 units, not for sale
Total 632 units. Land-owner units are not for sale.
Project facts
- 2 BHK
- 468
- 3 BHK
- 164
- Total units
- 632
- Buildings
- 2
- Land
- 2.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 546
- Land-owner share (not for sale)
- 86
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 37% | 0% | 96 | |
| 100% | 28% | 0% | 92 | |
| 100% | 0% | 0% | 0 | |
| 88% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Atul Life Phase I by Atul Projects India Pvt Ltd is a 632-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400086, launched in April 2024 with possession due in December 2030. 96 units booked out of 546 units for sale. The concrete structure (RCC) is 37% complete.
Read full summary
Atul Life Phase I is an SRA-sanctioned project by Atul Projects India Pvt Ltd in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800055779. It was launched in April 2024. It has 632 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 632 units, 546 are for sale and 86 are the land-owner's share, not for sale.
Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 37% complete, final finishes not started.
96 units booked out of 546 units for sale (18%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 28% to 37%.