Bitcon Elysium, Kandivali East
by Bitcon India Infrastructure Developers Private Limited · Kandivali East, Mumbai 400101 · Map
- Launched
- Apr 20244 yrs 9 mths promised
- Possession (MahaRERA)
- Jan 2029Not extended
- Concrete structure
- 55%Mid-construction
- Booked
- 35 of 24115% · 30 in Jul 2026
- Buildings
- 30.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 123
- 2 BHK
- 82
- 3 BHK
- 17
- Other units
- 19
- Total units
- 241
- Buildings
- 3
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 0% | 35 | |
| 100% | 0% | 0% | 30 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Bitcon Elysium by Bitcon India Infrastructure Developers Private Limited is a 241-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, launched in April 2024 with possession due in January 2029. 35 units booked out of total 241 units. The concrete structure (RCC) is 55% complete.
Read full summary
Bitcon Elysium is a BMC-sanctioned project by Bitcon India Infrastructure Developers Private Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800055839. It was launched in April 2024. It has 241 units in 3 buildings: 222 homes (1, 2 and 3 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is January 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 55% complete, final finishes not started.
35 units booked out of total 241 units (15%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 55%.